Electrical permits in Akron: who issues them and what they cost
Checked November 16, 2026 · independent guide, not an electrician
An electrical permit in Akron is a two-office job. The City of Akron reviews the project and registers the contractor. The County of Summit issues the permit and sends the inspector. Knowing that split saves a wasted trip, because a County permit cannot be issued until the City signs off.
Why the County issues Akron's electrical permits
The City's Plans and Permits page explains that in 2009 the City of Akron Building Department was combined with the Summit County Department of Building Standards. The County now reviews and issues permits for projects covered by the Ohio Residential Code and the Ohio Building Code, and County inspectors perform electrical, HVAC, plumbing and structural inspections inside Akron. (City of Akron, Plans and Permits)
The City keeps its own review. It says it reviews all projects inside city limits, that the County "can not issue building permits without Akron Approval," and that plans go to the City separately through its Plan Review and Permits portal. The City allows about 14 business days for plan review, longer for large projects. (City of Akron, Plans and Permits) At the County end, Building Standards says a permit typically takes "a couple of days" once the paperwork is complete. (Summit County Building Standards)
Both offices list the same street address, 1030 E. Tallmadge Ave. The City's Plans and Permits Center is at 330-375-2010 and the County's Building Standards office is at 330-630-7280. (City of Akron, Plans and Permits)
Which electrical code applies
Summit County inspects one-, two- and three-family homes against the Residential Code of Ohio. Its Chapter 34 adopts the National Electrical Code (NFPA 70) with Ohio amendments, in rule 4101:8-34-01. Ohio's official code site lists that rule as effective April 15, 2024. (Ohio Adm. Code 4101:8-34-01, rule text; Ohio Laws, Rule 4101:8-34-01) Summit County's notice explains that this rule was expected to bring in the 2023 edition of the NEC, after a drafting error about sump pumps delayed it from March 1, 2024. (Summit County Building Standards)
A few Ohio changes matter in Akron basements and yards:
- Unfinished basement areas need GFCI protection, but a single receptacle serving a sump pump does not, as long as a GFCI-protected duplex receptacle is within six feet of the pump.
- Ohio rewrote the NEC's surge-protection rule for dwelling services so it applies "where provided."
- Replacing equipment fed by an outdoor outlet means the outlet must then have GFCI protection.
Source: Ohio Adm. Code 4101:8-34-01.
Do I need a permit?
Summit County's code says no equipment or fixture regulated by the Building Code may be installed or altered without a permit, subject to the exceptions in the Ohio codes. (Summit County Codified Ordinances 1305.01 and 1305.02) The County's fee schedule shows the kinds of residential electrical work it expects to permit: new construction, interior alterations, extra circuits, temporary poles, service upgrades, interior and exterior lighting, miscellaneous repairs and meter pulls for siding. (Summit County, Electrical Permit Application)
The City answers two common questions directly. Finishing a basement needs permits from the County. A home security system does not need a permit. (City of Akron, Plans and Permits) For anything in between, call the County's electrical clerk before work starts.
The published Summit County fee schedule
These are the County's residential electrical fees on its current application form (revision 03.24). (Summit County, Electrical Permit Application)
| Residential item | Fee |
|---|---|
| Application fee | $60 |
| New construction | $4 per 100 sq ft |
| Interior alterations | $2 per 100 sq ft |
| Miscellaneous circuits | $12 each |
| Temporary pole, service upgrade, interior or exterior lighting | $40 each |
| Miscellaneous repairs | $40 |
| Meter pull for siding | $40, no application fee |
| Re-inspection, 1st and 2nd | $30 each |
| Re-inspection, 3rd | $60 |
| Re-inspection, 4th | $80 |
| Ohio Board of Building Standards fee | 1% of the residential subtotal |
The form says fees are paid in advance and are not refundable. As a worked example from the published fees only: a residential service upgrade with no other items is $60 plus $40, or $100, plus the 1% state fee. The County may add items the form does not list, and it asks applicants to call for any fee not shown.
Work done without a required permit costs more. Summit County may issue a permit after the fact, but at three times the normal fee. (Summit County Codified Ordinances 1305.04)
Who can apply
Most permits are pulled by the electrical contractor. Each County application must include the contractor's certificate of insurance, a federal ID number and, where applicable, a state license. The County no longer runs an annual contractor registration. That process, with its $145 fee and $10,000 bond, ended in March 2024. (Summit County Building Standards)
The City is different. It requires every contractor, in any trade, to register with the City of Akron when the work needs a permit. Registration needs an Akron tax registration number, a certificate of liability insurance, any state license the trade requires and, for contractors with employees, workers' compensation. Registration runs through the City portal, and the renewal period is June 1 to June 30. (City of Akron, Plans and Permits) Akron's income tax code, section 99.09, separately requires construction contractors to obtain a tax account number and a Certificate of Registration before starting work in the city. (City of Akron, Income Tax subcontractor report)
Homeowner permits
An owner may pull a Summit County permit for a home in the owner's name by signing a notarized Homeowners Affidavit. The County says to call its electrical clerk to verify first. (Summit County Building Standards) The affidavit allows an unpaid relative who is not a licensed contractor to do the work. (Summit County, Homeowners Affidavit) The owner must live in the house or plan to. Some work is off limits for owners and must be done by a state-licensed contractor, including the electrical service and meter from the utility connection to the house, and the grounding and bonding of pools, fountains, hot tubs and spas. (Summit County Codified Ordinances 1305.06)
Applying and scheduling inspections
Summit County moved its online permits and inspections to a portal called GovWell. The County says GovWell must be used for all new permit and inspection requests, and the older CityWorks portal now handles only requests made before September 25. The office is open 7:30 a.m. to 4:00 p.m., Monday to Friday, and takes inspections and drop-offs 8:00 a.m. to 3:00 p.m. It accepts cash and checks in person and credit cards online, and takes no cash after 3 p.m. (Summit County Building Standards)
For service work, the County's residential forms include an Overhead Electrical Service Diagram, an Underground Service Diagram and a Power Turn On Request. (Summit County, Residential Forms)
Checking an old or a neighbor's permit
Permits are public records. The County's permit search covers permits from October 2026 on. Older records come through a records request, and the County keeps a separate request form for records from before 2021. (Summit County Building Standards) If you are buying a house, the County says violations are handled by the local city, village or township. In Akron, the City's Housing Division (330-375-2366) answers questions about orders to comply. (City of Akron, Plans and Permits)
Frequently asked questions
How long is an Akron permit good for?
The City says its permits are valid for 12 months from issue if work has not begun, with a six-month extension available once work is under way. (City of Akron, Plans and Permits) County permit time limits are set in Summit County code section 1305.18.
Can I get a refund on an unused permit?
The City says expired and unused City permits are not refundable, and the County's form says its fees are not refundable.
Does Akron require an electrical inspection when a house sells?
No. The City does not require a point-of-sale inspection. (City of Akron, Plans and Permits)
Verify before you hire
Sources
- City of Akron, Plans and Permits
- Summit County Building Standards
- Summit County, Electrical Permit Application
- Summit County, Residential Forms
- Summit County, Homeowners Affidavit
- Summit County Codified Ordinances 1305.01 and 1305.02
- Ohio Adm. Code 4101:8-34-01, rule text
- Ohio Laws, Rule 4101:8-34-01
- City of Akron, Income Tax subcontractor report